United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in the USA (2020 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown635117.0 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

635 requests ยท page 3 of 13
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J1781, Iowa County
Onshore wind
300 MWUnder construction Iowa, WIMISO Jun 2020target 2027
Desert Sands
Battery storage
300 MWAgreement signed Riverside, CACAISO Apr 2020target 2035
Solar project J1710, Lee County
Solar
300 MWIn study Lee, ARMISO Jun 2020target 2026
Solar + storage project Company 189, Clark County
Solar + storage
300 MWPaused / redesign Clark, NVWest Feb 2020target 2025
Mammoth South Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Solar project J1712, Perry County
Solar
300 MWIn study Perry, ILMISO Jun 2020target 2025
Solar + storage project Q350, Yuma County
Solar + storage
300 MWUnder construction Yuma, AZWest Sep 2020target 2022
Other project 78, Apache County
Other
300 MWIn study Apache, AZWest Feb 2020target 2023
Solar project J1836, Callaway County
Solar
300 MWIn study Callaway, MOMISO Jun 2020target 2025
Dawson Solar
Solar ยท Deriva Energy Solar, LLC
300 MWIn study Mclean, ILPJM Sep 2020target 2024
Atrisco Solar II
Solar + storage
300 MWPaused / redesign Bernalillo, NMWest Oct 2020target 2023
Mammoth Central II Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Sep 2020target 2028
Jade Meadow III Solar Facility
Solar + storage
300 MWAgreement signed Garrett, MDPJM Sep 2020target 2028
Bellefield 3 Solar Farm
Solar + storage
300 MWAgreement signed Kern, CACAISO Apr 2020target 2027
Solar + storage project G0639, Douglas County
Solar + storage
300 MWIn study Douglas, WAWest Feb 2020target 2023
Burr Oak Solar
Solar ยท Leeward Renewable Energy Development, LLC
300 MWIn study Dekalb, ILPJM Aug 2020target 2023
Onshore wind project J1773, Lafayette County
Onshore wind
300 MWAgreement signed Lafayette, WIMISO Jun 2020target 2027
South Dixon Solar
Solar ยท Deriva Energy Solar, LLC
300 MWIn study Lee, ILPJM Mar 2020target 2022
Solar + storage project G0660, Grant County
Solar + storage
300 MWIn study Grant, WAWest Nov 2020target 2024
Solar project GEN-2020-054, Bowie County
Solar
298 MWAgreement signed Bowie, TXSPP Apr 2020target 2027
Fortuna Wind
Onshore wind ยท RWE Renewables Development, LLC
295 MWAgreement signed Jack, TXERCOT Mar 2020target 2026
Onshore wind project J1557, Sanilac County
Onshore wind
293 MWAgreement signed Sanilac, MIMISO Jun 2020target 2026
Sandow Solar
Solar ยท Sandow Lakes Ranch Solar I, LLC
287 MWIn study Milam, TXERCOT Sep 2020target 2028
Solar + storage project Q362, Pinal County
Solar + storage
275 MWIn study Pinal, NCWest Sep 2020target 2023
Gas project GEN-2020-038, Cass County
Gas
273 MWAgreement signed Cass, NESPP Apr 2020target 2028
Gas project GEN-2020-031, Sarpy County
Gas
273 MWAgreement signed Sarpy, NESPP Apr 2020target 2028
Battery storage project IC-906, Cherokee County
Battery storage
265 MWAgreement signed Cherokee, GASoutheast Oct 2020target 2026
Beacon Solar
Solar ยท Beacon Solar, LLC
260 MWIn study Rock Island, ILPJM Sep 2020target 2023
Mayapple Solar
Solar
260 MWAgreement signed Pulaski, INPJM Sep 2020target 2027
Captiva Energy Storage
Battery storage
257 MWAgreement signed Orange, CACAISO Apr 2020target 2028
Alila Solar
Solar + storage ยท Electra Energy Project, LLC
257 MWAgreement signed San Patricio, TXERCOT Oct 2020target 2028
Delamar Energy Storage
Battery storage
256 MWAgreement signed Clark, NVCAISO Apr 2020target 2027
Sierra Madre Solar
Solar ยท Sierra Madre Solar LLC
255 MWIn study Zapata, TXERCOT Jan 2020target 2027
Gipper Solar Farm
Solar ยท Gipper Solar Farm, LLC
255 MWIn study Whiteside, ILPJM Oct 2020target 2023
Pandora Solar
Solar
252 MWPaused / redesign Wilson, TXERCOT Jan 2020
Eval Storage
Battery storage ยท Hecate Grid East Valley Storage LLC
252 MWAgreement signed Cameron, TXERCOT Oct 2020target 2028
Cantaloupe Storage
Battery storage
251 MWPaused / redesign Reeves, TXERCOT Dec 2020
Tanglewood Solar
Solar ยท Brazoria Solar, LLC
251 MWAgreement signed Brazoria, TXERCOT Jul 2020target 2026
Solar + storage project GEN-2020-008, Stevens County
Solar + storage
250 MWAgreement signed Stevens, KSSPP Apr 2020target 2028
Other project Company KW, White Pine County
Other
250 MWPaused / redesign White Pine, NVWest Sep 2020target 2026
Samson Solar 3
Solar ยท Samson Solar Energy III LLC
250 MWAgreement signed Lamar, TXERCOT Jan 2020target 2026
Commerce Energy Storage 2
Battery storage
250 MWIn study Los Angeles, CACAISO Apr 2020target 2026
Solar + storage project IC-932, Glynn County
Solar + storage
250 MWPaused / redesign Glynn, GASoutheast Dec 2020target 2024
Battery storage project Q79, Kern County
Battery storage
250 MWIn study Kern, CAWest Oct 2020target 2026
Mill Point Solar
Solar + storage ยท ConnectGen Montgomery County LLC
250 MWIn study Montgomery, NYNYISO Jun 2020target 2028
Solar + storage project IC-933, Glynn County
Solar + storage
250 MWPaused / redesign Glynn, GASoutheast Dec 2020target 2024
Solar project J1573, Portage County
Solar
250 MWAgreement signed Portage, WIMISO Jun 2020target 2026
Goldfinch Solar
Solar ยท Goldfinch Solar, LLC
250 MWAgreement signed Mason, KYPJM Feb 2020target 2030
Solar + storage project Company KN, Humboldt County
Solar + storage
250 MWAgreement signed Humboldt, NVWest Aug 2020target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)