GAS · SPPGas project GEN-2020-031, Sarpy County
Gas project GEN-2020-031, Sarpy County is a 273 MW gas request with a signed interconnection agreement in the SPP interconnection queue, in Sarpy County, Nebraska, connecting to OPPD.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2020-031
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- Substation 1363; 161kV Substation
- Location
- Sarpy County, Nebraska
- Technology
- Gas: 273 MW
- Total requested
- 273 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 29 April 2020
- Proposed online date
- February 2028
Location
Marker shows the centre of Sarpy County; the queue data does not give exact sites.
Other requests in Sarpy County
- Gas project GEN-2020-025, Sarpy CountyGas · 255 MW · built
- Gas project GEN-2020-028, Sarpy CountyGas · 255 MW · built
- Gas project GEN-2020-024, Sarpy CountyGas · 425 MW · withdrawn
- Gas project GEN-2020-032, Sarpy CountyGas · 56.5 MW · withdrawn
- Gas project GEN-2020-026, Sarpy CountyGas · 56.5 MW · withdrawn
- Gas project GEN-2020-034, Sarpy CountyGas · 56.5 MW · withdrawn
- Gas project GEN-2020-029, Sarpy CountyGas · 56.5 MW · withdrawn
- Solar + storage project GEN-2020-033, Sarpy CountySolar + storage · 50.0 MW · withdrawn
- Solar + storage project GEN-2020-030, Sarpy CountySolar + storage · 50.0 MW · withdrawn
- Solar + storage project GEN-2020-027, Sarpy CountySolar + storage · 50.0 MW · withdrawn