πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2020-027, Sarpy County

Solar + storage project GEN-2020-027, Sarpy County is a 50.0 MW solar + storage request withdrawn in the SPP interconnection queue, in Sarpy County, Nebraska, connecting to OPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingMay 2024 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2020-027
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OPPD
Connection point (POI)
S1281 β€šΓ„Γ¬ S1362 161kV (S1363)
Location
Sarpy County, Nebraska
Technology
Solar: 50.0 MW Β· Battery
Total requested
50.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 April 2020
Proposed online date
May 2024
Came online
May 2024
Withdrawn
March 2024

Location

Marker shows the centre of Sarpy County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Sarpy County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem