United States › Grid › Interconnection queues › Kentucky
SOLAR · PJMGoldfinch Solar
Goldfinch Solar is a 250 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Mason County, Kentucky, connecting to EKPC.
Queue statusConsented
- PlanningQueued Feb 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2030 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AF2-111
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Developer
- Goldfinch Solar, LLC
- Connection point (POI)
- North Clark-Spurlock 345 kV
- Location
- Mason County, Kentucky
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Active
- Entered queue
- 28 February 2020
- Proposed online date
- June 2030
Location
Marker shows the centre of Mason County; the queue data does not give exact sites.
Other requests in Mason County
- Solar + storage project LGE-GIS-2021-017, Mason CountySolar + storage · 100 MW · suspended
- Mason Energy CenterGas · 1,150 MW · withdrawn
- Battery storage project AH1-756, Mason CountyBattery storage · 250 MW · withdrawn
- Solar + storage project AF2-245, Mason CountySolar + storage · 132 MW · withdrawn
- Solar project AE2-235, Mason CountySolar · 60.0 MW · withdrawn
- Solar project LGE-GIS-2019-026, Mason CountySolar · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem