United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2023 requests) โ page 29
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery Storage Battery storage |
108 MW | Withdrawn / abandoned |
| Wagon Wheel Energy Storage Battery storage |
106 MW | Withdrawn / abandoned |
| Charros Energy Center Solar + storage |
106 MW | Withdrawn / abandoned |
| Shuteye Peak Energy Storage Battery storage |
106 MW | Withdrawn / abandoned |
| Solar project GEN-2023-040, Thayer County Solar |
105 MW | Withdrawn / abandoned |
| Solar + storage project 23-238, Jefferson County Solar + storage |
105 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
105 MW | Withdrawn / abandoned |
| Birdrock Battery storage |
105 MW | Withdrawn / abandoned |
| Cuerno Grande Wind 2 Wind + storage |
105 MW | Withdrawn / abandoned |
| Solar project 23-237, Yamhill County Solar |
105 MW | Withdrawn / abandoned |
| Manzanita Inyaha Solar Solar + storage |
105 MW | Withdrawn / abandoned |
| ONNI Solar Solar + storage |
105 MW | Withdrawn / abandoned |
| Peach Storage Battery storage |
104 MW | Withdrawn / abandoned |
| Brackens BESS Battery storage ยท Brackens BESS |
104 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
103 MW | Withdrawn / abandoned |
| La Posta Battery storage |
103 MW | Withdrawn / abandoned |
| Millerton Battery storage |
103 MW | Withdrawn / abandoned |
| Freeride Solar Plus Solar + storage |
103 MW | Withdrawn / abandoned |
| Garda Battery storage |
103 MW | Withdrawn / abandoned |
| Lugano Battery storage |
103 MW | Withdrawn / abandoned |
| Delirium Dive Battery storage |
103 MW | Withdrawn / abandoned |
| Waverly (Formly Green Growth Hybrid) Solar + storage |
103 MW | Withdrawn / abandoned |
| Como Battery storage |
103 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
103 MW | Withdrawn / abandoned |
| Glacier Point Battery storage |
103 MW | Withdrawn / abandoned |
| Eyre Battery storage |
103 MW | Withdrawn / abandoned |
| Tuolumne Meadows Battery storage |
103 MW | Withdrawn / abandoned |
| Horsetail Falls Battery storage |
103 MW | Withdrawn / abandoned |
| Mackerel Energy Solar + storage |
103 MW | Withdrawn / abandoned |
| Burgundy BESS Battery storage ยท Burgundy BESS, LLC |
103 MW | Withdrawn / abandoned |
| Deer BESS Battery storage ยท GRS BESS Texas Two |
102 MW | Withdrawn / abandoned |
| Elion Energy Storage 2 Battery storage |
102 MW | Withdrawn / abandoned |
| Drifter Energy Storage 2 Battery storage |
102 MW | Withdrawn / abandoned |
| Noosa Energy Storage 2 Battery storage |
102 MW | Withdrawn / abandoned |
| Horse Wrangler Storage Battery storage ยท Horse Wrangler Solar Project, LLC |
102 MW | Withdrawn / abandoned |
| Lechon Battery storage |
102 MW | Withdrawn / abandoned |
| Driller Storage Battery storage |
102 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
102 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
102 MW | Withdrawn / abandoned |
| Mandorla (Formly Kirkwood Legacy Hybrid) Solar + storage |
102 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
102 MW | Withdrawn / abandoned |
| Crowded Star I BESS Other ยท Jones City Solar, LLC |
101 MW | Withdrawn / abandoned |
| Parthenon Energy Battery storage ยท Parthenon Energy, LLC |
101 MW | Withdrawn / abandoned |
| Palacios Bay Energy Storage Battery storage ยท Palacios Bay Energy Storage, LLC |
101 MW | Withdrawn / abandoned |
| Silver Fox Solar Solar ยท Industrial Lima Project LLC |
101 MW | Withdrawn / abandoned |
| Palm Bluff Energy Storage Other ยท Palm Bluff Energy Storage, LLC |
101 MW | Withdrawn / abandoned |
| Antoninus Energy Storage Battery storage ยท Antoninus Energy Storage, LLC |
101 MW | Withdrawn / abandoned |
| Port City Energy Storage Battery storage ยท Port City Energy Storage, LLC |
101 MW | Withdrawn / abandoned |
| Ambrose Energy Storage Other ยท Ambrose Energy Storage, LLC |
101 MW | Withdrawn / abandoned |
| Nerva Energy Storage Battery storage ยท Nerva Energy Storage, LLC |
101 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)486 ยท 198.6 GW
- West (non-ISO utilities)547 ยท 166.5 GW
- SPP (Southwest Power Pool)336 ยท 71.5 GW
- NYISO (New York)138 ยท 40.7 GW
- Southeast (non-ISO utilities)331 ยท 40.7 GW
- ERCOT (Texas)85 ยท 16.1 GW
- ISO-NE (New England)119 ยท 15.7 GW
- MISO (Midcontinent)10 ยท 1,143 MW
- PJM (Mid-Atlantic, Midwest)11 ยท 867 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)