BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 108 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Providence County, Rhode Island.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2023 (completed)
  2. Withdrawn / abandonedJan 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1472
Grid region
ISO-NE (New England)
Connection point (POI)
The Primary Point of Interconnection will be a direct interconnection to the 115-kV bus at Highland Park Substation owned by RI_NGRID. The Alternative Point of Interconnection will be located on the I
Location
Providence County, Rhode Island
Technology
Battery: 108 MW
Total requested
108 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
12 December 2023
Proposed online date
January 2027
Withdrawn
January 2024

Location

Marker shows the centre of Providence County; the queue data does not give exact sites.

Power plants in Rhode Island · Transmission lines in Rhode Island

Other requests in Providence County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem