ONSHORE WIND · ISO-NE

Johnston Landfill Wind

Johnston Landfill Wind is a 21.0 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Providence County, Rhode Island, connecting to NGRID.

Queue statusOperating
  1. PlanningQueued Nov 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
696
Grid region
ISO-NE (New England)
Utility / transmission owner
NGRID
Connection point (POI)
GRID Johnston substation, Circuit 2227
Location
Providence County, Rhode Island
Technology
Wind: 21.0 MW
Total requested
21.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
27 November 2017
Proposed online date
December 2018

Location

Marker shows the centre of Providence County; the queue data does not give exact sites.

Power plants in Rhode Island · Transmission lines in Rhode Island

Other requests in Providence County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem