United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTPort City Energy Storage
Port City Energy Storage is a 101 MW battery storage request withdrawn in the ERCOT interconnection queue, in San Patricio County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedNov 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 25INR0541
- Grid region
- ERCOT (Texas)
- Developer
- Port City Energy Storage, LLC
- Connection point (POI)
- Tap 138kV 80258 Mayo4A - 80260 Gila4A
- Location
- San Patricio County, Texas
- Technology
- Battery: 101 MW
- Total requested
- 101 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 24 October 2023
- Proposed online date
- December 2028
- Withdrawn
- November 2025
Location
Marker shows the centre of San Patricio County; the queue data does not give exact sites.
Other requests in San Patricio County
- SanPat Solar ISolar · 309 MW · agreement signed
- Alila SolarSolar + storage · 257 MW · agreement signed
- SanPat Solar IISolar · 256 MW · agreement signed
- Pintail Pass BESSBattery storage · 207 MW · agreement signed
- Jackalope SolarSolar · 156 MW · agreement signed
- Bowstring BESSBattery storage · 155 MW · agreement signed
- Hecate Energy Arkansas WindOnshore wind · 1,029 MW · in study
- Gregory Power Development SLFGas · 470 MW · in study
- Titus Low Carbon Ventures Solar 1Solar · 338 MW · in study
- Sunburst SolarSolar + storage · 302 MW · in study
- Gulf Gateway Storage OneSolar + storage · 301 MW · in study
- Gulf Gateway Solar OneSolar + storage · 301 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem