🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 102 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Hartford County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1400
Grid region
ISO-NE (New England)
Connection point (POI)
41.6317, -72.7289, Berlin 115 kV Substation
Location
Hartford County, Connecticut
Technology
Battery: 102 MW
Total requested
102 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
18 May 2023
Proposed online date
December 2026
Withdrawn
October 2025

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Hartford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem