United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

SOLAR Β· WEST

Solar project 23-237, Yamhill County

Solar project 23-237, Yamhill County is a 105 MW solar request withdrawn in the West interconnection queue, in Yamhill County, Oregon, connecting to Portland General Electric.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
23-237
Grid region
West (non-ISO utilities)
Utility / transmission owner
Portland General Electric
Connection point (POI)
Springbrook Substation
Location
Yamhill County, Oregon
Technology
Solar: 105 MW
Total requested
105 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
25 August 2023
Proposed online date
June 2026

Location

Marker shows the centre of Yamhill County; the queue data does not give exact sites.

Power plants in Oregon Β· Transmission lines in Oregon

Other requests in Yamhill County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem