BATTERY STORAGE Β· ERCOT

Burgundy BESS

Burgundy BESS is a 103 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
26INR0284
Grid region
ERCOT (Texas)
Developer
Burgundy BESS, LLC
Connection point (POI)
69 kV Prairie Hill (Bus# 107)
Technology
Battery: 103 MW
Total requested
103 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
4 October 2023
Proposed online date
July 2027

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem