🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Peach Storage

Peach Storage is a 104 MW battery storage request withdrawn in the CAISO interconnection queue, in Stanislaus County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2222
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
PIERCY 115 kV
Location
Stanislaus County, California
Technology
Battery: 104 MW
Total requested
104 MW
Service type
Network resource (NRIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
November 2031
Withdrawn
May 2025

Location

Marker shows the centre of Stanislaus County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Stanislaus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem