United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Paulsell Solar Energy Center

Paulsell Solar Energy Center is a 35.0 MW solar + storage request built and operating in the CAISO interconnection queue, in Stanislaus County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued May 2017 (completed)
  2. ConsentedJan 2021 (completed)
  3. Construction (completed)
  4. OperatingJun 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1350
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Crow Creek 60 kV
Location
Stanislaus County, California
Technology
Solar: 20.0 MW · Battery: 15.0 MW
Total requested
35.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
1 May 2017
Agreement signed
5 January 2021
Proposed online date
December 2019
Came online
June 2024

Location

Marker shows the centre of Stanislaus County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Stanislaus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem