SOLAR + STORAGE · CAISOPaulsell Solar Energy Center
Paulsell Solar Energy Center is a 35.0 MW solar + storage request built and operating in the CAISO interconnection queue, in Stanislaus County, California, connecting to PGAE.
Request details
- Queue ID
- 1350
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Crow Creek 60 kV
- Location
- Stanislaus County, California
- Technology
- Solar: 20.0 MW · Battery: 15.0 MW
- Total requested
- 35.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 1 May 2017
- Agreement signed
- 5 January 2021
- Proposed online date
- December 2019
- Came online
- June 2024
Location
Marker shows the centre of Stanislaus County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Stanislaus County
- Golden FlatsBattery storage · 365 MW · agreement signed
- Oakdale StorageBattery storage · 103 MW · agreement signed
- Crow Creek Solar 1 (Fka: Frontier Solar 1) (Fka As Scatec Westside Solar Ranch I And Stanislaus PV - Phase 1)Solar + storage · 40.0 MW · agreement signed
- AmaneceSolar + storage · 836 MW · in study
- GerasSolar + storage · 268 MW · in study
- Proxima SolarSolar + storage · 352 MW · built
- Central 40Solar · 40.0 MW · built
- HadselvilleSolar + storage · 816 MW · withdrawn
- Amanece SolarSolar + storage · 420 MW · withdrawn
- Mountain Valley StorageBattery storage · 306 MW · withdrawn
- Grape Valley StorageBattery storage · 306 MW · withdrawn
- NikovasterSolar + storage · 306 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem