SOLAR + STORAGE · CAISO

Geras

Geras is a 268 MW solar + storage request in interconnection study in the CAISO interconnection queue, in Stanislaus County, California, connecting to PGAE.

Queue statusIn planning
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2223
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
FINK SW STA 230 kV
Location
Stanislaus County, California
Technology
Solar: 134 MW · Battery: 134 MW
Total requested
268 MW
Service type
Network resource (NRIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Active
Entered queue
17 April 2023
Proposed online date
June 2028

Location

Marker shows the centre of Stanislaus County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Stanislaus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem