Queue requests in study in MISO (Midcontinent) — page 24

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,337302.2 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,337 requests · page 24 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J3231, Amite County
Solar + storage
100 MWIn study Amite, MSMISO Sep 2022target 2024
Battery storage project J2197, Clay County
Battery storage
100 MWIn study Clay, ILMISO Jan 2025target 2024
Battery storage project J1844, Washtenaw County
Battery storage
100 MWIn study Washtenaw, MIMISO Dec 2020target 2024
Solar + storage project J2456, Phillips County
Solar + storage
100 MWIn study Phillips, ARMISO Sep 2022target 2027
Solar project J1736, Dubois County
Solar
100 MWIn study Dubois, INMISO Jun 2020target 2023
Solar project J2739, Ohio County
Solar
100 MWIn study Ohio, KYMISO Sep 2022target 2026
Solar project J2742, White County
Solar
100 MWIn study White, ARMISO Sep 2022target 2026
Onshore wind project J2048, Benton County
Onshore wind
100 MWIn study Benton, INMISO Mar 2022target 2025
Solar project J3130, Marion County
Solar
100 MWIn study Marion, ILMISO Sep 2022target 2026
Solar project J2679, Livingston County
Solar
100 MWIn study Livingston, MIMISO Sep 2022target 2027
Solar project J4158, Dewitt County
Solar
100 MWIn study Dewitt, ILMISO Oct 2025target 2030
Surplus; J758
Other
100 MWIn study Calhoun, MIMISO Aug 2024target 2027
Solar + storage project J2193, Waushara County
Solar + storage
100 MWIn study Waushara, WIMISO Nov 2021target 2024
Surplus; J1190
Battery storage
100 MWIn study Lagrange, INMISO Jul 2025target 2027
Solar project J1795, Acadia Parish County
Solar
100 MWIn study Acadia Parish, LAMISO Jun 2020target 2025
Battery storage project J2195, Fayette County
Battery storage
100 MWIn study Fayette, ILMISO Jan 2025target 2024
Other project J4183
Other
99.9 MWIn study MISO target 2027
Battery storage project J4172, Wapello County
Battery storage
99.0 MWIn study Wapello, IAMISO Oct 2025target 2028
Solar project J1993, Columbia County
Solar
99.0 MWIn study Columbia, WIMISO Dec 2021target 2025
Solar project J2208, De Soto Parish County
Solar
99.0 MWIn study De Soto Parish, LAMISO Aug 2021target 2024
Replacing 95 MW of coal with BESS; Meramec 1, 2, 3, 4
Other
98.8 MWIn study St. Louis, MOMISO Dec 2024target 2025
Surplus; ALTE.QUILTBLCK
Battery storage
98.0 MWIn study Lafayette, WIMISO Mar 2025target 2027
Gas project J4145, Cerro Gordo County
Gas
98.0 MWIn study Cerro Gordo, IAMISO Oct 2025target 2028
Solar project J2918, Jasper County
Solar
97.0 MWIn study Jasper, ILMISO Sep 2022target 2025
Gas project J1359, Linn County
Gas
95.0 MWIn study Linn, IAMISO Apr 2019target 2025
Solar project J2920, Sabine Parish County
Solar
92.0 MWIn study Sabine Parish, LAMISO Sep 2022target 2024
Battery storage project J2455, La Crosse County
Battery storage
92.0 MWIn study La Crosse, WIMISO Sep 2022target 2026
Solar project J3777, Cheboygan County
Solar
91.8 MWIn study Cheboygan, MIMISO Apr 2024target 2028
Hoot Lake Battery Energy Storage System
Battery storage · Otter Tail Power Company
90.7 MWIn study Otter Tail, MNMISO Aug 2025target 2028
Surplus; J728
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Battery storage project J2913, Sargent County
Battery storage
90.0 MWIn study Sargent, NDMISO Sep 2022target 2025
Solar project J3953, Faulkner County
Solar
90.0 MWIn study Faulkner, ARMISO Nov 2024target 2028
Solar project J2794, Fayette County
Solar
90.0 MWIn study Fayette, ILMISO Aug 2022target 2027
Surplus; J717
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Solar project J2227, Trempealeau County
Solar
89.0 MWIn study Trempealeau, WIMISO Jul 2025target 2024
Solar + storage project J3223, Edwards County
Solar + storage
88.0 MWIn study Edwards, ILMISO Sep 2022target 2027
Gas project J3870, Vigo County
Gas
87.0 MWIn study Vigo, INMISO Dec 2024target 2002
Boswell Solar Project
Solar · Minnesota Power
86.8 MWIn study Itasca, MNMISO Aug 2025target 2027
Surplus; J1224/J1329
Other
85.1 MWIn study Washtenaw, MIMISO Oct 2024target 2028
Solar project J3914, Jefferson Davis Parish County
Solar
85.0 MWIn study Jefferson Davis Parish, LAMISO Oct 2024target 2030
Solar project J3988, Morehouse Parish County
Solar
85.0 MWIn study Morehouse Parish, LAMISO Oct 2024target 2030
Solar + storage project J4029, Mississippi County
Solar + storage
85.0 MWIn study Mississippi, ARMISO Jun 2025target 2025
Solar project J2874, Bay County
Solar
85.0 MWIn study Bay, MIMISO Aug 2022target 2025
Solar project J3653, Washtenaw County
Solar
80.0 MWIn study Washtenaw, MIMISO Apr 2024target 2028
Battery storage project J2879, Washington County
Battery storage
80.0 MWIn study Washington, MNMISO Sep 2022target 2025
Solar + storage project J3198, Barron County
Solar + storage
80.0 MWIn study Barron, WIMISO Sep 2022target 2027
Solar + storage project J2819, Red River Parish County
Solar + storage
80.0 MWIn study Red River Parish, LAMISO Oct 2025target 2025
Solar project J4009, Marshall County
Solar
80.0 MWIn study Marshall, MNMISO Apr 2025target 2030
Surplus; Old Gold
Other
80.0 MWIn study Worth, IAMISO Jun 2024target 2029
Solar project J2917, Ouachita Parish County
Solar
80.0 MWIn study Ouachita Parish, LAMISO Sep 2022target 2026
Page 24 of 27

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)