United States › Grid › Interconnection queues › Minnesota

BATTERY STORAGE · MISO

Hoot Lake Battery Energy Storage System

Hoot Lake Battery Energy Storage System is a 90.7 MW battery storage request in interconnection study in the MISO interconnection queue, in Otter Tail County, Minnesota, connecting to Otter Tail Power Company.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
E0005
Grid region
MISO (Midcontinent)
Utility / transmission owner
Otter Tail Power Company
Developer
Otter Tail Power Company
Connection point (POI)
Hoot Lake 115 kV Substation
Location
Otter Tail County, Minnesota
Technology
Battery: 90.7 MW
Total requested
90.7 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Active; Post GIA Status: Not started
Queue status
Active
Entered queue
6 August 2025
Proposed online date
May 2028

Location

Marker shows the centre of Otter Tail County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Otter Tail County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem