Solar project J4091, Otter Tail County is a 295 MW solar request in interconnection study in the MISO interconnection queue, in Otter Tail County, Minnesota, connecting to OTTER TAIL POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4091
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
ALEXANDRIA - BISON 345.0kV
Location
Otter Tail County, Minnesota
Technology
Solar: 295 MW
Total requested
295 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
6 October 2025
Proposed online date
June 2030

Location

Marker shows the centre of Otter Tail County; the queue data does not give exact sites.