SOLAR Β· SPP

Solar project GEN-2024-269, Otter Tail County

Solar project GEN-2024-269, Otter Tail County is a 315 MW solar request withdrawn in the SPP interconnection queue, in Otter Tail County, Minnesota, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-269
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Morris - Moorhead 230kV Line
Location
Otter Tail County, Minnesota
Technology
Solar: 315 MW
Total requested
315 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
1 March 2025
Proposed online date
December 2030
Withdrawn
December 2025

Location

Marker shows the centre of Otter Tail County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Otter Tail County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem