United States › Grid › Interconnection queues › Minnesota

OTHER · MISO

Replace 350 MW of ALTW.FPL_DAEC Unit with Solar; Duane Arnold

Replace 350 MW of ALTW.FPL_DAEC Unit with Solar; Duane Arnold is a 350 MW other request withdrawn in the MISO interconnection queue, in Otter Tail County, Minnesota, connecting to Alliant Energy West.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
R1006
Grid region
MISO (Midcontinent)
Utility / transmission owner
Alliant Energy West
Connection point (POI)
Hoot Lake 115KV
Location
Otter Tail County, Minnesota
Technology
Solar: 350 MW · Other
Total requested
350 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
15 February 2021
Proposed online date
July 2023

Location

Marker shows the centre of Otter Tail County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Otter Tail County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem