Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,283285.2 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,283 requests · page 23 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Altamaha Green Energy
Other
70.0 MWIn study Wayne, GASoutheast Aug 2024target 2028
Solar project 962965, Lenoir County
Solar
70.0 MWIn study Lenoir, NCSoutheast Oct 2024
Battery storage project GEN-2024-SR8, Greeley County
Battery storage
70.0 MWIn study Greeley, NESPP Apr 2024target 2026
Solar project 963472, Robeson County
Solar
70.0 MWIn study Robeson, NCSoutheast Sep 2024
Solar project PIS058, Emery County
Solar · PacifiCorp
70.0 MWIn study Emery, UTWest May 2024target 2026
Symank Solar
Solar · BT Symank Solar, LLC
66.6 MWIn study Bosque, TXERCOT Nov 2024target 2027
Solar project 963044, Cumberland County
Solar · Duke Energy Progress LLC
65.0 MWIn study Cumberland, NCSoutheast Sep 2024
Solar project J3529, Mahnomen County
Solar
64.0 MWIn study Mahnomen, MNMISO May 2024target 2028
Gas project GEN-2024-019, Gage County
Gas
62.0 MWIn study Gage, NESPP Oct 2024target 2030
Dewdrop Wind
Onshore wind · Dewdrop Wind LLC
62.0 MWIn study Chautauqua, NYNYISO Sep 2024target 2029
Gas project GEN-2024-017, Lancaster County
Gas
62.0 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project PIS090, Utah County
Gas · PacifiCorp
62.0 MWIn study Utah, UTWest Oct 2024target 2026
Little Star Solar
Solar · RWE Clean Energy Development, LLC
61.6 MWIn study Bastrop, TXERCOT Jul 2024target 2026
Beaverhead Solar SLF
Solar + storage · Beaverhead Solar, LLC
61.5 MWIn study Jim Wells, TXERCOT Aug 2024target 2027
Beaverhead Storage SLF
Solar + storage · Beaverhead Solar, LLC
61.5 MWIn study Jim Wells, TXERCOT Aug 2024target 2027
Centennial Solar
Solar · Centennial AD 8 LLC
61.4 MWIn study Menard, TXERCOT Jan 2024target 2029
Battery storage project S0029, Crook County
Battery storage
60.8 MWIn study Crook, ORWest Feb 2024target 2026
Fallstone Solar SLF
Solar + storage · Fallstone Solar, LLC
60.6 MWIn study Falls, TXERCOT Dec 2024target 2028
Hondo Arroyo Solar
Solar + storage · Hondo Creek Solar, LLC
60.4 MWIn study Medina, TXERCOT Jun 2024target 2028
Tipperary Solar
Solar · Tippsol
60.2 MWIn study Schleicher, TXERCOT Jun 2024target 2028
Stonewall Solar
Solar + storage · Stonewall PV, LLC
60.2 MWIn study Stonewall, TXERCOT May 2024target 2029
Cayuga Solar
Solar · Cayuga Lake Solar, LLC
60.0 MWIn study Tompkins, NYNYISO Sep 2024target 2028
Gas project 657, Muhlenberg County
Gas
60.0 MWIn study Muhlenberg, KYSoutheast Oct 2024target 2030
Taylor Creek Two
Solar
60.0 MWIn study Orange, FLSoutheast Feb 2024target 2026
Kce NY 21
Battery storage · KCE NY 21, LLC
60.0 MWIn study Suffolk, NYNYISO Aug 2024target 2029
Town Line Solar Phase II
Solar + storage · RWE Solar Development, LLC
60.0 MWIn study Sullivan, NYNYISO Sep 2024target 2030
Battery storage project IC-1267, Floyd County
Battery storage
57.5 MWAgreement signed Floyd, GASoutheast Mar 2024target 2026
Onshore wind project J3592, Sunflower County
Onshore wind
57.0 MWIn study Sunflower, MSMISO Apr 2024target 2028
Battery storage project S0030, Crook County
Battery storage
55.0 MWIn study Crook, ORWest Feb 2024target 2026
Replacing 55 MW with 29 MW Natural Gas/Fuel Oil; Blue Lake Unit 3
Gas
55.0 MWIn study Scott, MNMISO May 2024target 2025
Gas project 656, Benton County
Gas
54.0 MWIn study Benton, MSSoutheast Oct 2024target 2030
Donna BESS
Solar + storage · Donna Solar LLC
53.9 MWIn study Hidalgo, TXERCOT Mar 2024target 2029
Paloma Energy Center BESS
Solar + storage · Harrison Street Development, LLC
53.6 MWIn study Colorado, TXERCOT Feb 2024target 2027
Battery storage project GEN-2024-SR13, Bryan County
Battery storage
52.2 MWIn study Bryan, OKSPP May 2024target 2026
Solar project 111, Polk County
Solar
52.0 MWIn study Polk, FLSoutheast Mar 2024target 2027
Fluvanna Max BESS SLF
Solar + storage · Fluvanna Max Solar LLC
51.8 MWIn study Scurry, TXERCOT Dec 2024target 2029
Findley BESS
Solar + storage · Gransolar Texas Sixteen, LLC
51.7 MWIn study Limestone, TXERCOT Feb 2024target 2028
Solar project 268, Richland County
Solar
51.0 MWIn study Richland, SCSoutheast Jun 2024target 2027
Battery storage project 24-242, Polk County
Battery storage
50.0 MWIn study Polk, ORWest Apr 2024target 2028
Solar project 956852, Darlington County
Solar
50.0 MWIn study Darlington, SCSoutheast Jun 2024
Gas project 2024-G6, Mohave County
Gas
50.0 MWIn study Mohave, AZWest Aug 2024target 2027
Solar project 963122, Laurens County
Solar
50.0 MWIn study Laurens, SCSoutheast Sep 2024
Battery storage project 956218, Nash County
Battery storage · Duke Energy Progress LLC
50.0 MWIn study Nash, NCSoutheast Jun 2024
Sandlot IFB
Battery storage · Sandlot Energy LLC
50.0 MWIn study Suffolk, NYNYISO Sep 2024target 2028
Battery storage project GEN-2024-SR17, Kay County
Battery storage
50.0 MWIn study Kay, OKSPP Dec 2024target 2027
Surplus; G905
Other
50.0 MWIn study Midland, MIMISO Aug 2024target 2026
Solar project J2891, Kenosha County
Solar
50.0 MWIn study Kenosha, WIMISO Jan 2024target 2026
Battery storage project BHCT G50, Pueblo County
Battery storage · Black Hills Colorado Electric, LLC
50.0 MWIn study Pueblo, COWest Jun 2024target 2026
Azalea Wind 1
Onshore wind · Azalea Wind LLC
50.0 MWIn study Schuyler, NYNYISO Oct 2024target 2029
Azalea Wind 2
Onshore wind · Azalea Wind LLC
50.0 MWIn study Schuyler, NYNYISO Oct 2024target 2029
Page 23 of 26

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)