United States › Grid › Interconnection queues › Minnesota
SOLAR · MISOSolar project J3529, Mahnomen County
Solar project J3529, Mahnomen County is a 64.0 MW solar request in interconnection study in the MISO interconnection queue, in Mahnomen County, Minnesota, connecting to OTTER TAIL POWER COMPANY.
Queue statusIn planning
- PlanningQueued May 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3529
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- OTTER TAIL POWER COMPANY
- Connection point (POI)
- Mahnomen - Winger 115.0kV
- Location
- Mahnomen County, Minnesota
- Technology
- Solar: 64.0 MW
- Total requested
- 64.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 20 May 2024
- Proposed online date
- May 2028
Location
Marker shows the centre of Mahnomen County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem