🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

SOLAR · MISO

Solar project J3529, Mahnomen County

Solar project J3529, Mahnomen County is a 64.0 MW solar request in interconnection study in the MISO interconnection queue, in Mahnomen County, Minnesota, connecting to OTTER TAIL POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued May 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3529
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Mahnomen - Winger 115.0kV
Location
Mahnomen County, Minnesota
Technology
Solar: 64.0 MW
Total requested
64.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
20 May 2024
Proposed online date
May 2028

Location

Marker shows the centre of Mahnomen County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem