Solar project 963044, Cumberland County

Solar project 963044, Cumberland County is a 65.0 MW solar request in interconnection study in the Southeast interconnection queue, in Cumberland County, North Carolina, connecting to Duke Energy Progress.

Queue statusIn planning
  1. PlanningQueued Sep 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
963044
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Developer
Duke Energy Progress LLC
Connection point (POI)
Clinton - Vander 115kV
Location
Cumberland County, North Carolina
Technology
Solar: 65.0 MW
Total requested
65.0 MW
Service type
Network resource (NRIS)
Study phase
Phase 2 Cluster Study - In Progress
Queue status
Active
Entered queue
24 September 2024

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Cumberland County