🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Paloma Energy Center BESS

Paloma Energy Center BESS is a 53.6 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Colorado County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0148
Grid region
ERCOT (Texas)
Developer
Harrison Street Development, LLC
Connection point (POI)
Tap 138kV 57640 Rock Island - 57639 Sheridan
Location
Colorado County, Texas
Technology
Battery: 53.6 MW · Battery
Total requested
53.6 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
7 February 2024
Proposed online date
June 2027

Location

Marker shows the centre of Colorado County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Colorado County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem