United States › Grid › Interconnection queues › Oregon
BATTERY STORAGE · WESTBattery storage project S0030, Crook County
Battery storage project S0030, Crook County is a 55.0 MW battery storage request in interconnection study in the West interconnection queue, in Crook County, Oregon, connecting to PacifiCorp.
Queue statusIn planning
- PlanningQueued Feb 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- S0030
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Baldwin Road substation
- Location
- Crook County, Oregon
- Technology
- Battery: 55.0 MW
- Total requested
- 55.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 23 February 2024
- Proposed online date
- June 2026
Location
Marker shows the centre of Crook County; the queue data does not give exact sites.
Other requests in Crook County
- Solar + storage project C2-158, Crook CountySolar + storage · 199 MW · agreement signed
- Solar + storage project C2-114, Crook CountySolar + storage · 199 MW · agreement signed
- Battery storage project C2-178, Crook CountyBattery storage · 199 MW · agreement signed
- Solar project 734, Crook CountySolar · 102 MW · agreement signed
- Solar + storage project TCS-44, Crook CountySolar + storage · 80.0 MW · agreement signed
- Solar + storage project C2-07, Crook CountySolar + storage · 80.0 MW · agreement signed
- Solar project C2-06, Crook CountySolar · 80.0 MW · agreement signed
- Solar + storage project C2-08, Crook CountySolar + storage · 80.0 MW · agreement signed
- Solar + storage project C2-09, Crook CountySolar + storage · 80.0 MW · agreement signed
- Solar + storage project 731, Crook CountySolar + storage · 55.0 MW · agreement signed
- Solar + storage project TCS-45, Crook CountySolar + storage · 40.0 MW · agreement signed
- Solar + storage project TCS-54, Crook CountySolar + storage · 40.0 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem