United States › Grid › Interconnection queues › New York
ONSHORE WIND · NYISOAzalea Wind 2
Azalea Wind 2 is a 50.0 MW onshore wind request in interconnection study in the NYISO interconnection queue, in Schuyler County, New York, connecting to NYSEG.
Queue statusIn planning
- PlanningQueued Oct 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C24-370
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Azalea Wind LLC
- Connection point (POI)
- Montour Falls to Coddington Road 115kV
- Location
- Schuyler County, New York
- Technology
- Wind: 50.0 MW
- Total requested
- 50.0 MW
- Queue status
- Active
- Entered queue
- 15 October 2024
- Proposed online date
- December 2029
Location
Marker shows the centre of Schuyler County; the queue data does not give exact sites.
Other requests in Schuyler County
- Azalea Wind 1Onshore wind · 50.0 MW · in study
- Watkins Glen SolarSolar · 50.0 MW · in study
- Watkins Glen EastOnshore wind · 151 MW · withdrawn
- Watkins Glen WindOnshore wind · 122 MW · withdrawn
- Azalea Wind 1Onshore wind · 50.0 MW · withdrawn
- Azalea Wind 2Onshore wind · 50.0 MW · withdrawn
- Christmas TreeSolar + storage · 25.0 MW · withdrawn
- Meads Hill SolarSolar · 20.0 MW · withdrawn
- 47763 CayutaSolar · 20.0 MW · withdrawn
- Cronk Solar LLCSolar + storage · 19.9 MW · withdrawn
- Cayuta Add-onBattery storage · 2.0 MW · withdrawn
- Cayuta Add-onBattery storage · 2.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem