United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISOCayuta Add-on
Cayuta Add-on is a 2.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Schuyler County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1618
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Nexamp Solar
- Connection point (POI)
- Cayuta - Ridge Road 34.5 kV line, Line#501
- Location
- Schuyler County, New York
- Technology
- Battery: 2.0 MW
- Total requested
- 2.0 MW
- Queue status
- Withdrawn
- Entered queue
- 10 October 2023
Location
Marker shows the centre of Schuyler County; the queue data does not give exact sites.
Other requests in Schuyler County
- Azalea Wind 1Onshore wind · 50.0 MW · in study
- Azalea Wind 2Onshore wind · 50.0 MW · in study
- Watkins Glen SolarSolar · 50.0 MW · in study
- Watkins Glen EastOnshore wind · 151 MW · withdrawn
- Watkins Glen WindOnshore wind · 122 MW · withdrawn
- Azalea Wind 1Onshore wind · 50.0 MW · withdrawn
- Azalea Wind 2Onshore wind · 50.0 MW · withdrawn
- Christmas TreeSolar + storage · 25.0 MW · withdrawn
- Meads Hill SolarSolar · 20.0 MW · withdrawn
- 47763 CayutaSolar · 20.0 MW · withdrawn
- Cronk Solar LLCSolar + storage · 19.9 MW · withdrawn
- Cayuta Add-onBattery storage · 2.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem