BATTERY STORAGE · NYISO

Cayuta Add-on

Cayuta Add-on is a 2.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Schuyler County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2023 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1540
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Nexamp
Connection point (POI)
The POI will be located 1.78mi from Cayuta 34.5kV substation and 11.78mi from Ridge Road 230kV substation. Utilizes the same gen-tie line to deliver power to the POI at existing 34.5 kV pole located a
Location
Schuyler County, New York
Technology
Battery: 2.0 MW
Total requested
2.0 MW
Queue status
Withdrawn
Entered queue
20 March 2023
Withdrawn
May 2023

Location

Marker shows the centre of Schuyler County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Schuyler County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem