United States › Grid › Interconnection queues › New York

ONSHORE WIND · NYISO

Watkins Glen East

Watkins Glen East is a 151 MW onshore wind request withdrawn in the NYISO interconnection queue, in Schuyler County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2011 (completed)
  2. Withdrawn / abandonedOct 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
366
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
NextEra Energy Resources, LLC
Connection point (POI)
Montour Falls Substation
Location
Schuyler County, New York
Technology
Wind: 151 MW
Total requested
151 MW
Queue status
Withdrawn
Entered queue
2 August 2011
Withdrawn
October 2012

Location

Marker shows the centre of Schuyler County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Schuyler County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem