United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOMeads Hill Solar
Meads Hill Solar is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Schuyler County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2018 (completed)
- Withdrawn / abandonedNov 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 736
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Empire State Solar, LLC
- Connection point (POI)
- Montour Falls - Greenidge 115kV
- Location
- Schuyler County, New York
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 12 June 2018
- Withdrawn
- November 2018
Location
Marker shows the centre of Schuyler County; the queue data does not give exact sites.
Other requests in Schuyler County
- Azalea Wind 1Onshore wind Β· 50.0 MW Β· in study
- Azalea Wind 2Onshore wind Β· 50.0 MW Β· in study
- Watkins Glen SolarSolar Β· 50.0 MW Β· in study
- Watkins Glen EastOnshore wind Β· 151 MW Β· withdrawn
- Watkins Glen WindOnshore wind Β· 122 MW Β· withdrawn
- Azalea Wind 1Onshore wind Β· 50.0 MW Β· withdrawn
- Azalea Wind 2Onshore wind Β· 50.0 MW Β· withdrawn
- Christmas TreeSolar + storage Β· 25.0 MW Β· withdrawn
- 47763 CayutaSolar Β· 20.0 MW Β· withdrawn
- Cronk Solar LLCSolar + storage Β· 19.9 MW Β· withdrawn
- Cayuta Add-onBattery storage Β· 2.0 MW Β· withdrawn
- Cayuta Add-onBattery storage Β· 2.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem