United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESInterconnection queue in the USA (2021 requests) โ page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Dovetail Solar 2 Solar + storage ยท Hecate Energy Dovetail Solar 2 LLC |
666 MW | In study |
| Yuha Desert Battery Storage Battery storage |
633 MW | In study |
| Cady Solar Solar + storage |
626 MW | Agreement signed |
| Solar project J2261, Jackson County Solar |
625 MW | In study |
| Solar project J2262, Jackson County Solar |
625 MW | In study |
| Cherry Lane Hybrid Solar + storage |
621 MW | In study |
| Remy Solar + storage |
617 MW | In study |
| Larrea Solar Solar + storage |
614 MW | In study |
| Australis Solar + storage |
614 MW | Agreement signed |
| Cornucopia Hybrid Solar + storage |
605 MW | Agreement signed |
| Hiru Solar Solar + storage ยท Hecate Energy Hazel LLC |
604 MW | In study |
| Solar + storage project Company 201, Clark County Solar + storage |
600 MW | Paused / redesign |
| Solar project G0669, Crook County Solar |
600 MW | In study |
| Solar + storage project Company 200, Clark County Solar + storage |
600 MW | Paused / redesign |
| Battery storage project 622, Malheur County Battery storage ยท Owyhee Energy Storage, LLC |
600 MW | Agreement signed |
| Battery storage project IC-974, Fulton County Battery storage |
600 MW | Paused / redesign |
| Solar + storage project 90, Pima County Solar + storage |
600 MW | In study |
| Wind + storage project Company LV, White Pine County Wind + storage |
600 MW | Paused / redesign |
| Solar project G0673, Crook County Solar |
600 MW | In study |
| Soleil Cantil Solar + storage |
597 MW | In study |
| Solar + storage project Q80, Kern County Solar + storage |
590 MW | In study |
| Solar + storage project Q387, Navajo County Solar + storage |
588 MW | In study |
| Twin Palms Solar Solar + storage |
576 MW | Agreement signed |
| Other project 110, Garfield County Other |
560 MW | In study |
| Bull Creek (Osceola Generating Station) Gas |
555 MW | Agreement signed |
| Solar + storage project Company LW, Mineral County Solar + storage |
550 MW | Paused / redesign |
| Solar + storage project Q85, Juab County Solar + storage ยท Intermountain Power Agency |
550 MW | In study |
| Redonda Solar + storage |
542 MW | Agreement signed |
| Sagebrush Energy Storage Battery storage |
528 MW | In study |
| Elmax Power Station Gas ยท Elmax Generating, LLC |
519 MW | Agreement signed |
| Alta Casa Storage Battery storage |
515 MW | Agreement signed |
| Greasewood Energy Storage Battery storage |
513 MW | Agreement signed |
| Conduit Energy Storage Battery storage |
513 MW | Agreement signed |
| Rosa Storage Battery storage |
512 MW | In study |
| Solar project GEN-2021-030, Linn County Solar |
510 MW | In study |
| Bayside Solar Solar |
509 MW | Paused / redesign |
| Dovetail Storage Solar + storage ยท Hecate Energy Dovetail Storage LLC |
509 MW | In study |
| Battery Storage Battery storage |
508 MW | Agreement signed |
| Outpost Storage Solar + storage ยท Hecate Energy Outpost Storage LLC |
508 MW | In study |
| Lock Storage Battery storage |
508 MW | Agreement signed |
| Tehuacana Creek Solar Solar + storage ยท Tehuacana Creek Solar LLC |
505 MW | Agreement signed |
| Drifter Energy Storage Battery storage |
505 MW | Agreement signed |
| Onshore wind project GEN-2021-070, Hodgeman County Onshore wind |
504 MW | In study |
| Spectrum Energy Storage Battery storage |
504 MW | Agreement signed |
| Delilah Energy Storage Battery storage |
504 MW | Agreement signed |
| Harley Hand Storage Solar + storage ยท Hecate Energy Harley Hand Solar LLC |
503 MW | In study |
| Sterling Solar + storage |
500 MW | In study |
| Solar + storage project Q29, Maricopa County Solar + storage |
500 MW | In study |
| Onshore wind project C1-35, Carbon County Onshore wind ยท Lucky Star Wind, LLC |
500 MW | Agreement signed |
| Solar + storage project Company ME, Lyon County Solar + storage |
500 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)228 ยท 68.8 GW
- CAISO (California)138 ยท 66.9 GW
- ERCOT (Texas)207 ยท 39.5 GW
- MISO (Midcontinent)136 ยท 23.7 GW
- Southeast (non-ISO utilities)63 ยท 12.7 GW
- SPP (Southwest Power Pool)44 ยท 9,029 MW
- ISO-NE (New England)20 ยท 3,998 MW
- PJM (Mid-Atlantic, Midwest)49 ยท 2,072 MW
- NYISO (New York)11 ยท 991 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)