🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arizona

SOLAR + STORAGE · WEST

Solar + storage project 90, Pima County

Solar + storage project 90, Pima County is a 600 MW solar + storage request in interconnection study in the West interconnection queue, in Pima County, Arizona, connecting to Tucson Electric Power Company.

Queue statusIn planning
  1. PlanningQueued Jan 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
90
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tucson Electric Power Company
Connection point (POI)
Pinal West - South Loop 345kV
Location
Pima County, Arizona
Technology
Solar: 400 MW · Battery: 200 MW
Total requested
600 MW
Service type
Network resource (NRIS)
Study phase
IA EXECUTION IN PROGRESS
Queue status
Active
Entered queue
27 January 2021
Proposed online date
December 2025

Location

Marker shows the centre of Pima County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Pima County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem