United States › Grid › Interconnection queues › California
BATTERY STORAGE · CAISODelilah Energy Storage
Delilah Energy Storage is a 504 MW battery storage request with a signed interconnection agreement in the CAISO interconnection queue, in Contra Costa County, California, connecting to PGAE.
Queue statusConsented
- PlanningQueued Apr 2021 (completed)
- ConsentedSep 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2032 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1875
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Pittsburg-Tesla #1 230 kV Line
- Location
- Contra Costa County, California
- Technology
- Battery: 504 MW
- Total requested
- 504 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 15 April 2021
- Agreement signed
- 13 September 2025
- Proposed online date
- July 2032
Location
Marker shows the centre of Contra Costa County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Contra Costa County
- Steel City Battery StorageBattery storage · 675 MW · agreement signed
- Allegheny Energy StorageBattery storage · 353 MW · agreement signed
- Black Diamond ES2Battery storage · 179 MW · agreement signed
- Harmony Storage 2Battery storage · 308 MW · in study
- Sherman Energy StorageBattery storage · 256 MW · in study
- Gateway Generating Facility (Fka Contra Costa Power Plant Project)Gas · 590 MW · built
- Black Diamond Energy StorageBattery storage · 200 MW · built
- Marsh Landing Generation Station - Simple Cycle UnitsGas · 100 MW · built
- Los Medanos Energy CenterGas · 72.0 MW · built
- Buena Vista RepowerOnshore wind · 37.5 MW · built
- Columbia Solar Energy 2 Fka Columbia Solar Energy IISolar · 20.0 MW · built
- Vasco Wind ProjectOnshore wind · 3.1 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem