Queue statusOperating
  1. PlanningQueued Mar 2011 (completed)
  2. ConsentedJul 2013 (completed)
  3. Construction (completed)
  4. OperatingOct 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
687
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Pittsburg-Kirker-Columbia Steel 115 kV Line
Location
Contra Costa County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
31 March 2011
Agreement signed
16 July 2013
Proposed online date
December 2012
Came online
October 2015

Location

Marker shows the centre of Contra Costa County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Contra Costa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem