🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

GAS · CAISO

Marsh Landing Generation Station - Simple Cycle Units

Marsh Landing Generation Station - Simple Cycle Units is a 100 MW gas request built and operating in the CAISO interconnection queue, in Contra Costa County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Mar 2008 (completed)
  2. ConsentedNov 2018 (completed)
  3. Construction (completed)
  4. OperatingMay 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
320
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Contra Costa Substation 230kV switchyard
Location
Contra Costa County, California
Technology
Gas: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
12 March 2008
Agreement signed
27 November 2018
Proposed online date
May 2013
Came online
May 2013

Location

Marker shows the centre of Contra Costa County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Contra Costa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem