Los Medanos Energy Center

Los Medanos Energy Center is a 72.0 MW gas request built and operating in the CAISO interconnection queue, in Contra Costa County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Apr 2013 (completed)
  2. ConsentedNov 2015 (completed)
  3. Construction (completed)
  4. OperatingMar 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
963
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Pittsburg Substation 115 kV bus
Location
Contra Costa County, California
Technology
Gas: 72.0 MW
Total requested
72.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
30 April 2013
Agreement signed
19 November 2015
Proposed online date
January 2014
Came online
March 2019

Location

Marker shows the centre of Contra Costa County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Contra Costa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem