United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) — page 17

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,646350.1 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,646 requests · page 17 of 33
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J2689, Liberty County
Solar + storage
180 MWIn study Liberty, TXMISO Jul 2025target 2026
Solar + storage project J3003, Mason County
Solar + storage
180 MWIn study Mason, ILMISO Sep 2022target 2025
Surplus; J1007
Battery storage
180 MWIn study Crittenden, ARMISO Apr 2025target 2026
Solar project J919, Jackson County
Solar
180 MWUnder construction Jackson, ARMISO Jun 20172023
Onshore wind project J2654, Clinton County
Onshore wind
180 MWIn study Clinton, INMISO Sep 2022target 2026
Onshore wind project J3702, Mitchell County
Onshore wind
180 MWIn study Mitchell, IAMISO Mar 2024target 2028
Solar project J1677, Macon County
Solar
180 MWIn study Macon, ILMISO Jun 2020target 2026
Solar project J3167, Fulton County
Solar
180 MWIn study Fulton, ILMISO Sep 2022target 2026
Solar project J2578, Tuscola County
Solar
180 MWIn study Tuscola, MIMISO Sep 2022target 2026
Solar project J2847, Starke County
Solar
180 MWIn study Starke, INMISO Sep 2022target 2026
Solar project J1658, Hillsdale County
Solar
180 MWAgreement signed Hillsdale, MIMISO May 2025target 2025
Onshore wind project J1437, Carroll County
Onshore wind
180 MWUnder construction Carroll, ARMISO Apr 2019target 2024
Solar project J3342, Vermilion County
Solar
180 MWIn study Vermilion, ILMISO Apr 2024target 2028
Au Gres Solar Project
Solar · DTE Electric
180 MWIn study Arenac, MIMISO Aug 2025target 2028
Onshore wind project J2247, Marshall County
Onshore wind
178 MWIn study Marshall, ILMISO Mar 2022target 2024
Solar project J4043, Eaton County
Solar
178 MWIn study Eaton, MIMISO Aug 2025target 2028
Onshore wind project J2571, Tunica County
Onshore wind
177 MWIn study Tunica, MSMISO Sep 2022target 2024
Onshore wind project J3743, Tuscola County
Onshore wind
176 MWIn study Tuscola, MIMISO Apr 2024target 2027
Solar project J1721, Vigo County
Solar
175 MWIn study Vigo, INMISO Jun 2020target 2026
Solar project J3059, Midland County
Solar
175 MWIn study Midland, MIMISO Sep 2022target 2026
Solar project J2258, Adams County
Solar
175 MWIn study Adams, ILMISO Mar 2022target 2024
Onshore wind project J3909, Gratiot County
Onshore wind
175 MWIn study Gratiot, MIMISO Feb 2025target 2030
Solar + storage project J3254, Pulaski County
Solar + storage
175 MWIn study Pulaski, ILMISO Apr 2024target 2026
Solar project J2876, Arenac County
Solar
175 MWIn study Arenac, MIMISO Sep 2022target 2025
Onshore wind project J2437, Lee County
Onshore wind
175 MWIn study Lee, ARMISO Sep 2022target 2027
Solar project J3340, Vermilion County
Solar
175 MWIn study Vermilion, ILMISO Mar 2024target 2028
Onshore wind project J3905, Tazewell County
Onshore wind
175 MWIn study Tazewell, ILMISO Mar 2025target 2030
Solar project J2629, Newton County
Solar
175 MWIn study Newton, TXMISO Sep 2022target 2026
Solar + storage project J2273, Clinton County
Solar + storage
175 MWIn study Clinton, ILMISO Jul 2025target 2024
Solar + storage project J3732, Saline County
Solar + storage
175 MWIn study Saline, ILMISO Apr 2024target 2026
Battery storage project J3904, Tazewell County
Battery storage
175 MWIn study Tazewell, ILMISO Mar 2025target 2030
Solar + storage project J2266, Edgar County
Solar + storage
175 MWIn study Edgar, ILMISO Jun 2025target 2025
Onshore wind project J2988, Humboldt County
Onshore wind
175 MWIn study Humboldt, IAMISO Sep 2022target 2025
Solar project J2288, Ralls County
Solar
175 MWIn study Ralls, MOMISO Jan 2025target 2025
Solar project J643, Jasper County
Solar
175 MWAgreement signed Jasper, INMISO May 20162023
Solar project J1583, Iberville Parish County
Solar
175 MWAgreement signed Iberville Parish, LAMISO Jun 2020target 2025
Solar project J586, Mississippi County
Solar
175 MWAgreement signed Mississippi, ARMISO May 20162024
Solar project J1611, Morrison County
Solar
174 MWIn study Morrison, MNMISO Jun 2020target 2026
Gas project G018, Trimble County
Gas
174 MWIn study Trimble, KYMISO Dec 1999target 2004
Gas project G016, Trimble County
Gas
174 MWIn study Trimble, KYMISO Dec 1999target 2005
Gas project G017, Trimble County
Gas
174 MWIn study Trimble, KYMISO Dec 1999target 2004
Gas project G069, Trimble County
Gas
174 MWIn study Trimble, KYMISO Dec 2000target 2001
Coal project G003, Trimble County
Coal
174 MWIn study Trimble, KYMISO Dec 1998target 2004
Coal project G002, Trimble County
Coal
174 MWIn study Trimble, KYMISO Dec 1998target 2016
Solar + storage project J2127, Jefferson Davis County
Solar + storage
173 MWIn study Jefferson Davis, MSMISO Aug 2021target 2027
Solar + storage project J4170, Richland County
Solar + storage
172 MWIn study Richland, NDMISO Oct 2025target 2029
Solar project J3382, Piatt County
Solar
171 MWIn study Piatt, ILMISO Apr 2024target 2028
Onshore wind project J3926, Webster County
Onshore wind
170 MWIn study Webster, IAMISO Mar 2025target 2030
Solar project J2675, Gladwin County
Solar
170 MWIn study Gladwin, MIMISO Sep 2022target 2025
Solar project J1297, Shiawassee County
Solar
170 MWUnder construction Shiawassee, MIMISO Apr 2019target 2024
Page 17 of 33

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)