Solar + storage project J2127, Jefferson Davis County

Solar + storage project J2127, Jefferson Davis County is a 173 MW solar + storage request in interconnection study in the MISO interconnection queue, in Jefferson Davis County, Mississippi, connecting to COOPERATIVE ENERGY.

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2127
Grid region
MISO (Midcontinent)
Utility / transmission owner
COOPERATIVE ENERGY
Connection point (POI)
Silver Creek 115kV
Location
Jefferson Davis County, Mississippi
Technology
Solar: 173 MW · Battery
Total requested
173 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
23 August 2021
Agreement signed
8 December 2025
Proposed online date
July 2027

Location

Marker shows the centre of Jefferson Davis County; the queue data does not give exact sites.

Power plants in Mississippi · Transmission lines in Mississippi

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem