United States › Grid › Interconnection queues › Minnesota
SOLAR · MISOSolar project J1611, Morrison County
Solar project J1611, Morrison County is a 174 MW solar request in interconnection study in the MISO interconnection queue, in Morrison County, Minnesota, connecting to MINNESOTA POWER INC..
Queue statusIn planning
- PlanningQueued Jun 2020 (current stage)
- ConsentedAug 2024 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1611
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MINNESOTA POWER INC.
- Connection point (POI)
- Langdon 115 kV Sub
- Location
- Morrison County, Minnesota
- Technology
- Solar: 174 MW
- Total requested
- 174 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 23 June 2020
- Agreement signed
- 9 August 2024
- Proposed online date
- September 2026
Location
Marker shows the centre of Morrison County; the queue data does not give exact sites.
Other requests in Morrison County
- Onshore wind project J4157, Morrison CountyOnshore wind · 150 MW · in study
- Onshore wind project J042, Morrison CountyOnshore wind · 200 MW · withdrawn
- Solar project J1143, Morrison CountySolar · 100 MW · withdrawn
- Solar project J735, Morrison CountySolar · 100 MW · withdrawn
- Onshore wind project G596, Morrison CountyOnshore wind · 1.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem