United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project J042, Morrison County
Onshore wind project J042, Morrison County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Morrison County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2009 (completed)
- Withdrawn / abandonedJan 2013 (project stopped here)
- ConsentedJan 2013 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J042
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- GRE Benton - Brainerd 230kV
- Location
- Morrison County, Minnesota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 12 May 2009
- Agreement signed
- 30 January 2013
- Proposed online date
- March 2013
- Withdrawn
- January 2013
Location
Marker shows the centre of Morrison County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Morrison County
- Solar project J1611, Morrison CountySolar Β· 174 MW Β· in study
- Onshore wind project J4157, Morrison CountyOnshore wind Β· 150 MW Β· in study
- Solar project J1143, Morrison CountySolar Β· 100 MW Β· withdrawn
- Solar project J735, Morrison CountySolar Β· 100 MW Β· withdrawn
- Onshore wind project G596, Morrison CountyOnshore wind Β· 1.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem