United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project G596, Morrison County
Onshore wind project G596, Morrison County is a 1.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Morrison County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2006 (completed)
- Withdrawn / abandonedApr 2006 (project stopped here)
- ConsentedApr 2006 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G596
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Morrison County, Minnesota
- Technology
- Wind: 1.0 MW
- Total requested
- 1.0 MW
- Queue status
- Withdrawn
- Entered queue
- 14 February 2006
- Agreement signed
- 5 April 2006
- Proposed online date
- December 2009
- Withdrawn
- April 2006
Location
Marker shows the centre of Morrison County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Morrison County
- Solar project J1611, Morrison CountySolar Β· 174 MW Β· in study
- Onshore wind project J4157, Morrison CountyOnshore wind Β· 150 MW Β· in study
- Onshore wind project J042, Morrison CountyOnshore wind Β· 200 MW Β· withdrawn
- Solar project J1143, Morrison CountySolar Β· 100 MW Β· withdrawn
- Solar project J735, Morrison CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem