🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project J4157, Morrison County

Onshore wind project J4157, Morrison County is a 150 MW onshore wind request in interconnection study in the MISO interconnection queue, in Morrison County, Minnesota, connecting to MINNESOTA POWER INC..

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4157
Grid region
MISO (Midcontinent)
Utility / transmission owner
MINNESOTA POWER INC.
Connection point (POI)
Iron Ridge - Benton 345kV
Location
Morrison County, Minnesota
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
3 October 2025
Proposed online date
September 2030

Location

Marker shows the centre of Morrison County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Morrison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem