🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Illinois

SOLAR · MISO

Solar project J3340, Vermilion County

Solar project J3340, Vermilion County is a 175 MW solar request in interconnection study in the MISO interconnection queue, in Vermilion County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3340
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Rossville 138kV on the Hoopeston to Vermilion 138kV Line
Location
Vermilion County, Illinois
Technology
Solar: 175 MW
Total requested
175 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
18 March 2024
Proposed online date
September 2028

Location

Marker shows the centre of Vermilion County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Vermilion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem