United States › Grid › Interconnection queues › Illinois

ONSHORE WIND · MISO

Onshore wind project H094, Vermilion County

Onshore wind project H094, Vermilion County is a 99.0 MW onshore wind request built and operating in the MISO interconnection queue, in Vermilion County, Illinois.

Queue statusOperating
  1. PlanningQueued Jul 2008 (completed)
  2. ConsentedJan 2011 (completed)
  3. Construction (completed)
  4. OperatingDec 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
H094
Grid region
MISO (Midcontinent)
Connection point (POI)
22 N Range: 12 West/1/50 miles west of Rossville, IL/138kV line
Location
Vermilion County, Illinois
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
28 July 2008
Agreement signed
4 January 2011
Proposed online date
December 2010
Came online
December 2010

Location

Marker shows the centre of Vermilion County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Vermilion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem