United States › Grid › Interconnection queues › Illinois
SOLAR · MISOSolar project J2233, Vermilion County
Solar project J2233, Vermilion County is a 100 MW solar request in interconnection study in the MISO interconnection queue, in Vermilion County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusIn planning
- PlanningQueued Jun 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2233
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- 7BUNSONVILLE - 7SIDNEY 345.0kV
- Location
- Vermilion County, Illinois
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 June 2022
- Proposed online date
- August 2024
Location
Marker shows the centre of Vermilion County; the queue data does not give exact sites.
Other requests in Vermilion County
- Surplus; AMIL.TILT1-4Solar · 188 MW · in study
- Solar project J3342, Vermilion CountySolar · 180 MW · in study
- Solar project J3340, Vermilion CountySolar · 175 MW · in study
- Onshore wind project J3341, Vermilion CountyOnshore wind · 100 MW · in study
- Onshore wind project H100, Vermilion CountyOnshore wind · 200 MW · built
- Onshore wind project H094, Vermilion CountyOnshore wind · 99.0 MW · built
- Onshore wind project J196, Vermilion CountyOnshore wind · 50.0 MW · built
- Gas project J388, Vermilion CountyGas · 800 MW · withdrawn
- Other project J1656, Vermilion CountyOther · 412 MW · withdrawn
- Solar project J3562, Vermilion CountySolar · 300 MW · withdrawn
- Onshore wind project V3-032, Vermilion CountyOnshore wind · 200 MW · withdrawn
- Solar project J3371, Vermilion CountySolar · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem