Solar interconnection queue in the USA — page 16

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 16 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 191, Sumter County
Solar
200 MWIn study Sumter, SCSoutheast Jun 2023target 2027
Solar project J3464, Story County
Solar
200 MWIn study Story, IAMISO Apr 2024target 2028
Solar project J1379, Montcalm County
Solar
200 MWAgreement signed Montcalm, MIMISO Apr 2019target 2025
Solar project J2075, Liberty County
Solar
200 MWIn study Liberty, TXMISO Aug 2021target 2028
Solar project J2002, Washington County
Solar
200 MWIn study Washington, IAMISO Aug 2021target 2024
Solar project J1550, Branch County
Solar
200 MWAgreement signed Branch, MIMISO Jun 2020target 2025
Solar project J3633, Sanilac County
Solar
200 MWIn study Sanilac, MIMISO Apr 2024target 2028
Solar project J3837, Van Buren County
Solar
200 MWIn study Van Buren, MIMISO Dec 2024target 2029
Steward Creek Solar
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Mar 2020target 2023
Solar project J2987, Greene County
Solar
200 MWIn study Greene, INMISO Sep 2022target 2025
Solar project J3256, Clark County
Solar
200 MWIn study Clark, ILMISO Apr 2024target 2028
Solar project J1076, St. James Parish County
Solar
200 MWUnder construction St. James Parish, LAMISO Mar 2018target 2022
Solar project 25-IC-1368, Mobile County
Solar
200 MWIn study Mobile, ALSoutheast Apr 2025target 2029
Solar project 8, Grant County
Solar
200 MWIn study Grant, WAWest Jul 2022
Solar project J3803, Monroe County
Solar
200 MWIn study Monroe, MIMISO Apr 2024target 2028
Stem Solar
Solar · Innovative Solar 134, LLC
200 MWIn study Swisher, TXERCOT Feb 2020target 2025
Solar project J1378, Fountain County
Solar
200 MWAgreement signed Fountain, INMISO Apr 2019target 2024
Old Route 66 Power
Solar
200 MWAgreement signed Guadalupe, NMWest Jun 2021target 2024
Solar project J1424, Beauregard Parish County
Solar
200 MWUnder construction Beauregard Parish, LAMISO Apr 2019target 2024
Solar project J1299, Scott County
Solar
200 MWUnder construction Scott, MOMISO Apr 2019target 2025
Solar project J1562, Mississippi County
Solar
200 MWAgreement signed Mississippi, ARMISO Jun 2020target 2025
Solar project IC-1088, Lee County
Solar
200 MWAgreement signed Lee, GASoutheast Nov 2022target 2027
Solar project J1431, St. James Parish County
Solar
200 MWAgreement signed St. James Parish, LAMISO Apr 2019target 2024
Solar project J2667, Sanilac County
Solar
200 MWIn study Sanilac, MIMISO Sep 2022target 2025
Solar project J3095, Ford County
Solar
200 MWIn study Ford, ILMISO Sep 2022target 2025
Solar project J4092, Beauregard Parish County
Solar
200 MWIn study Beauregard Parish, LAMISO Oct 2025target 2030
Lynn Bark Energy Center
Solar
200 MWAgreement signed Martin, KYPJM Nov 2019target 2029
Solar project J3287, Osceola County
Solar
200 MWIn study Osceola, MIMISO Apr 2024target 2028
Solar project J2848, Hamilton County
Solar
200 MWIn study Hamilton, INMISO Nov 2025target 2025
Solar project J1190, Clinton County
Solar
200 MWAgreement signed Clinton, IAMISO Jan 2019target 2025
Solar project BHCT G49, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jun 2024target 2026
South Dixon Solar
Solar · Deriva Energy Solar, LLC
200 MWIn study Lee, ILPJM Sep 2019target 2022
Solar project IC-1097, Emanuel County
Solar
200 MWAgreement signed Emanuel, GASoutheast Nov 2022target 2028
Solar project J2676, Huron County
Solar
200 MWIn study Huron, MIMISO Sep 2022target 2025
Solar project J2228, Concordia Parish County
Solar
200 MWIn study Concordia Parish, LAMISO Dec 2021target 2027
Solar project J2486, Monroe County
Solar
200 MWIn study Monroe, MIMISO Sep 2022target 2025
Solar project GEN-2024-168, Fillmore County
Solar
200 MWIn study Fillmore, NESPP Mar 2025target 2033
Solar project J3847, Jefferson County
Solar
200 MWIn study Jefferson, ILMISO Jan 2025target 2029
Solar project J1849, Hardin County
Solar
200 MWIn study Hardin, TXMISO Nov 2021target 2028
Solar project J2181, Mississippi County
Solar
200 MWIn study Mississippi, ARMISO Jul 2022target 2027
Solar project J2298, Greene County
Solar
200 MWIn study Greene, ARMISO Nov 2021target 2028
Solar project J1684, Starke County
Solar
200 MWIn study Starke, INMISO Aug 2023target 2029
Solar project IC-1094, Irwin County
Solar
200 MWAgreement signed Irwin, GASoutheast Nov 2022target 2028
Blooming Grove Solar Energy Center
Solar
200 MWAgreement signed Livingston, ILPJM Sep 2018target 2028
Solar project J3522, Cass County
Solar
200 MWIn study Cass, NDMISO Mar 2024target 2028
Solar project J1062, Washtenaw County
Solar
200 MWAgreement signed Washtenaw, MIMISO Mar 2018target 2023
Rodeo Solar
Solar · Core Solar SPV I, LLC
200 MWAgreement signed Andrews, TXERCOT Jun 2017target 2026
Solar project J1558, Pope County
Solar
200 MWIn study Pope, ARMISO Jun 2020target 2026
NY125C - Little Salmon Solar
Solar · Little Salmon Solar LLC
200 MWIn study Franklin, NYNYISO Aug 2024target 2028
Solar project J3959, Grundy County
Solar
200 MWIn study Grundy, MOMISO Apr 2025target 2029
Page 16 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)