United States › Grid › Interconnection queues › Illinois

SOLAR · MISO

Solar project J3256, Clark County

Solar project J3256, Clark County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Clark County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3256
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
4GALLATIN - 4KANSAS 138.0kV
Location
Clark County, Illinois
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
13 April 2024
Proposed online date
September 2028

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem