United States › Grid › Interconnection queues › Illinois

SOLAR · MISO

Solar project J1382, Clark County

Solar project J1382, Clark County is a 150 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Clark County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedApr 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1382
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Hutsonville - Neoga 138 kV Line tap
Location
Clark County, Illinois
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
24 April 2024
Proposed online date
May 2025

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem