SOLAR Β· MISOSolar project J2158, Clark County
Solar project J2158, Clark County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Clark County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2158
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Hutsonville - Neoga 138KV
- Location
- Clark County, Illinois
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 24 August 2021
- Proposed online date
- August 2024
- Withdrawn
- December 2025
Location
Marker shows the centre of Clark County; the queue data does not give exact sites.
Other requests in Clark County
- Solar project J1180, Clark CountySolar Β· 75.0 MW Β· under construction
- Solar + storage project J1263, Clark CountySolar + storage Β· 409 MW Β· agreement signed
- Solar project J1382, Clark CountySolar Β· 150 MW Β· agreement signed
- Solar project J1475, Clark CountySolar Β· 75.0 MW Β· agreement signed
- Solar project J3950, Clark CountySolar Β· 340 MW Β· in study
- Solar project J3256, Clark CountySolar Β· 200 MW Β· in study
- Battery storage project J2170, Clark CountyBattery storage Β· 150 MW Β· in study
- Battery storage project J3695, Clark CountyBattery storage Β· 150 MW Β· in study
- Battery storage project J2159, Clark CountyBattery storage Β· 50.0 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem