United States › Grid › Interconnection queues › Illinois
SOLAR · MISOSolar project J3847, Jefferson County
Solar project J3847, Jefferson County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Jefferson County, Illinois.
Queue statusIn planning
- PlanningQueued Jan 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3847
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Walton Shell Substation 138KV
- Location
- Jefferson County, Illinois
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 3 January 2025
- Proposed online date
- June 2029
Location
Marker shows the centre of Jefferson County; the queue data does not give exact sites.
Other requests in Jefferson County
- Solar project J1241, Jefferson CountySolar · 200 MW · agreement signed
- Battery storage project J3031, Jefferson CountyBattery storage · 200 MW · in study
- Battery storage project J2497, Jefferson CountyBattery storage · 300 MW · withdrawn
- Solar project J3878, Jefferson CountySolar · 300 MW · withdrawn
- Battery storage project J1655, Jefferson CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem