United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in PJM (Mid-Atlantic, Midwest) — page 16

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,248140.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,248 requests · page 16 of 25
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AG2-616, Salem County
Solar · Goldenrod Energy Center, LLC
50.0 MWIn study Salem, NJPJM Mar 2025target 2023
Battery storage project AH2-371, Jay County
Battery storage
50.0 MWIn study Jay, INPJM Mar 2022target 2026
Sunridge Solar
Solar
50.0 MWAgreement signed Rockingham, VAPJM Dec 2018target 2026
Maple Hill-Fiddlers 1 SP (Bear Rock)
Solar · CPV Maple Hill Solar, LLC
50.0 MWIn study Cambria, PAPJM Dec 2019target 2021
Mark Center Solar Project
Solar
49.9 MWAgreement signed Defiance, OHPJM Nov 2016target 2026
White Trillium
Solar
49.9 MWAgreement signed Van Wert, OHPJM Mar 2019target 2027
Solar + storage project AH2-408, Wood County
Solar + storage
49.9 MWIn study Wood, OHPJM Mar 2022target 2025
Eaton OH Solar
Solar
49.9 MWAgreement signed Preble, OHPJM Feb 2017target 2027
Solar project AI1-091, Seneca County
Solar
49.9 MWIn study Seneca, OHPJM Aug 2022target 2025
Solar project AI1-092, Butler County
Solar
49.9 MWIn study Butler, OHPJM Aug 2022target 2025
Solar project AH1-282, Morrow County
Solar · Woodbury Solar, LLC
49.9 MWIn study Morrow, OHPJM Mar 2025target 2025
Timber Road Solar Park III
Solar
49.9 MWAgreement signed Paulding, OHPJM Sep 2020target 2029
Solar + storage project AI1-150, Butler County
Solar + storage
49.9 MWIn study Butler, OHPJM Sep 2022target 2027
Solar project AF2-298, Montgomery County
Solar
49.9 MWAgreement signed Montgomery, OHPJM Mar 2020target 2028
Steubenville Solar
Solar
49.5 MWPaused / redesign Jefferson, OHPJM Nov 2017target 2027
Recreation Solar
Solar
49.5 MWPaused / redesign Guernsey, OHPJM Sep 2018target 2025
Solar project AH2-159, Highland County
Solar
49.0 MWIn study Highland, OHPJM Mar 2022target 2025
Woodsdale Renewable Energy Center
Solar
49.0 MWAgreement signed Butler, OHPJM Mar 2019target 2026
Solar project AJ1-022, Mecklenburg County
Solar
49.0 MWIn study Mecklenburg, VAPJM Jun 2023target 2027
Concho Solar I
Solar
49.0 MWPaused / redesign Queen Anne's, MDPJM Mar 2018target 2024
Solar + storage project AH2-239, Trumbull County
Solar + storage
49.0 MWIn study Trumbull, OHPJM Mar 2022target 2027
Switchgrass Solar 1
Solar
49.0 MWPaused / redesign Accomack, VAPJM Mar 2019target 2025
Solar project AI2-161, Vermillion County
Solar
48.0 MWIn study Vermillion, INPJM Mar 2023target 2025
Solar project AI2-151, Logan County
Solar
48.0 MWIn study Logan, ILPJM Feb 2023target 2025
Solar project AI2-162, Whitley County
Solar
48.0 MWIn study Whitley, INPJM Mar 2023target 2025
Solar project AI2-417, Dekalb County
Solar
48.0 MWIn study Dekalb, ILPJM Mar 2023target 2026
Great Bend
Solar
48.0 MWAgreement signed Meigs, OHPJM Oct 2016target 2025
Solar + storage project AH2-346, Hancock County
Solar + storage
47.5 MWIn study Hancock, OHPJM Mar 2022target 2025
Gardenia
Solar + storage · Gardenia Solar, LLC
46.5 MWIn study Clarion, PAPJM Feb 2025target 2024
Solar project AI1-011, Cumberland County
Solar
46.0 MWIn study Cumberland, VAPJM Apr 2022target 2026
South Branch Solar
Solar
46.0 MWPaused / redesign Hancock, OHPJM Jul 2020target 2025
Porter Mill Solar
Solar
45.8 MWAgreement signed Wicomico, MDPJM Jan 2017target 2026
Lake Trout Solar
Solar
45.0 MWAgreement signed Blackford, INPJM Mar 2020target 2028
Solar + storage project AH2-242, Montgomery County
Solar + storage
45.0 MWIn study Montgomery, OHPJM Mar 2022target 2027
Battery storage project AH2-241, City Of Chesapeake County
Battery storage
45.0 MWIn study City Of Chesapeake, VAPJM Mar 2022target 2027
Waller Solar I
Solar
45.0 MWAgreement signed Lancaster, VAPJM Jun 2019target 2027
Gas project AH2-269A, Prince George's County
Gas
45.0 MWIn study Prince George's, MDPJM Mar 2022target 2026
Battery storage project AI2-277, Greensville County
Battery storage
45.0 MWIn study Greensville, VAPJM Mar 2023target 2026
Glen Falls Facility
Gas
45.0 MWAgreement signed Harrison, WVPJM Mar 2018target 2029
Solar + storage project AH2-344, Marion County
Solar + storage
45.0 MWIn study Marion, OHPJM Mar 2022target 2025
Solar project AH2-166, Fulton County
Solar
45.0 MWIn study Fulton, OHPJM Mar 2022target 2025
Waller Solar I
Solar
45.0 MWAgreement signed Lancaster, VAPJM Jun 2020target 2027
Solar project AI2-150, Huntington County
Solar
44.4 MWIn study Huntington, INPJM Feb 2023target 2025
Peach Bottom Units #2 & #3
Nuclear
44.0 MWAgreement signed York, PAPJM Apr 20162019
Solar + storage project AH2-028, Pickaway County
Solar + storage
44.0 MWIn study Pickaway, OHPJM Nov 2021target 2025
Solar project AI2-159, Miami County
Solar
43.5 MWIn study Miami, OHPJM Mar 2023target 2027
Solar project AI2-421, Dekalb County
Solar
43.2 MWIn study Dekalb, INPJM Mar 2023target 2027
Solar project AI2-426, Allen County
Solar
43.2 MWIn study Allen, INPJM Mar 2023target 2027
Vinton Energy Storage
Battery storage
42.0 MWPaused / redesign Vinton, OHPJM Aug 2018target 2026
Solar project AF1-302, Jefferson County
Solar
42.0 MWAgreement signed Jefferson, PAPJM Sep 2019target 2027
Page 16 of 25

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)